Steam production started at the Uzbekneftegaz GTL plant

DOWNSTREAM CENTRAL ASIA

Steam production started at the Uzbekneftegaz GTL plant

Mehriddin Abdullayev, Chairman of the Board of Uzbekneftegaz JSC, visited the Construction Site of the GTL plant on March 18, 2021, where he reviewed implementation of the investment project. Source: UZDaily

The Project is nearing completion now, having reached a 95 - per cent overall progress. Construction and installation works are being completed at the Construction Site, asphalt laying has been commenced with paint and insulation works and landscaping progress being well under way. Pre-commissioning works and testing of pipelines and equipment are carried out in the Plant’s processing areas. Over 9.5 thousand people have been working at the Construction Site and more than 500 pieces of equipment are in use.

On 18 March 2021, the first boiler plant was put into operation and steam production started at the Uzbekneftegaz GTL Plant with participation of the Chairman of the Board of Uzbekneftegaz JSC rd.

The generated steam will be used for the Plant process and production needs. In addition, steam turbine generators will soon be brought onstream, contributing to production of the Plant’s own electrical power thanks to the steam energy.

Pre-commissioning and commissioning works are going on intensively at the Uzbekneftegaz GTL Plant.

Relevant news

DOWNSTREAM CENTRAL ASIA
Uzbekneftegaz and Shell discus areas of cooperation
Uzbekneftegaz and Shell discus areas of cooperation.
DOWNSTREAM CENTRAL ASIA
Uzbekistan reveals new deadline for its gas-to-liquids project
Uzbekistan has set a new deadline for the commissioning project in the Kashkadarya region.
CIS GAS MONETISATION
Sibur, Gazprom Neft and Uzbekneftegaz consider investing in Shurtan Gas Chemical Complex
The cooperation agreements were signed by the 2 Russian companies and Uzbekneftegaz last week during an official visit to Moscow by a delegation from Uzbekistan’s energy ministry.
DOWNSTREAM CENTRAL ASIA
UNG 'open to suggestions' on Chinaz upgrade
Uzbekneftegaz is planning to upgrade its Chinaz Refinery.
DOWNSTREAM CENTRAL ASIA
MTO licensor expected by year end
Uzbekneftegaz expects to select and sign a contract with a licensor for its methanol-to-olefins.
DOWNSTREAM CENTRAL ASIA
Shurtan expansion to speed up after GTL commissioning
Shurtan Gas Chemicals Complex will gain pace once construction at the Oltin Yo’l gas-to-liquids plant ends.